380kV Double Circuit Overhead Transmission Line from Fadhili 380/230kV Substation to Future Shamlul Switching Station
Approximately 217.4km of 380kV Overhead Transmission Line Double Circuit, Vertical Configuration, Lattice Steel Towers using four (4) 547.4mm2 Aluminum Conductor with OPGWs/OGW
Including All Civil Works related to the project
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
380kV Double Circuit Overhead Transmission Line from Future Shamlul Switching Station to Sudair Substation No.9011
Approximately 196km of 380kV Overhead Transmission Line Double Circuit, Vertical Configuration, Lattice Steel Towers using four (4) 547.4mm2 Aluminum Conductor with OPGWs/OGW
Including All Civil Works Related to the project
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Installation of 69kV Underground and Fiber Optic Cables Between Overhead to Underground Transition Tower
AL-MAHA 69/13.8kV Substation -Two (2) new 69kV Underground Cable Circuits (1x1Cx1200mm2, Copper Conductor, Cable per Phase) between the proposed overhead to underground Transition Tower,
One (1) overhead to underground transition latticed steel tower,
three (3)km, 12-core OPGW from transition tower to existing tower no.22
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
69kV Underground Transmission line & fiber optic cables to Al-Khobar Al-Sahelia Bayonia #2
Royal Palace Substation -Installation of 10.8 KM cable from RAKAH S/S to AL-KHOBAR AL SAHELIA, THUQBAH to BAYONIAH and DAMMAM P/P to ROYAL Palace Substation
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Reinforcement of 230 kV XLPE Cable in 3 Nos. Jubail Substation -
Installation of 230kV 1Cx2500mm2 Power Cables, SF6 Indoor Termination, Outdoor Sealing Ends, Link boxes with Arresters, Link Boxes without Arresters, Temperature Monitoring System, 230kV Line Protection, Extension of SOE, SCADA System, Communication System
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Construction of 110/13.8kV BANI MALIK, EEH-2 and WAZIRIAH Substations
Installation of 110kV, 40kA/1sec., 2500A, GIS, Double busbar (2500A Bus Coupler & Bus Section Bay, 1000A Cable Feeder/Transformer Bays), Power Transformer (31.5/40MVA 110/15kV Transformer)
Client
Saudi Electricity Company Western Operating Area (SEC-WOA)
SENAEYAH 230/69/13.8KV BSP, SENAEYAH-Dhahran central / Bqaiq 230kV T/Lines
Senaeyah-Dammam Industrial Estate 69kV U/G Lines
230kV GIS Single or Three Phase Enclosure type, 63kA sym. Fault level,
69kV GIS single phase enclosure type of three phase enclosure type, 40kA, 155/205/255MVA, 230/69/13.8kV Transformers, 30/40MVA, 69/13.8kV Power Transformers, 230kV Single Core CU XLPE Cable with Terminations Kits
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Reinforcement of 132kV Substation # 8501, 8808 & 8812
Installation of 132kV Switchgear, Protection & Control Equipment, Telecommunication & Marshalling Kiosk, Multicore Cables, Civil Works & Security System
Client
Saudi Electricity Company Central Operating Area (SEC-COA)
Installation of 30/40MVA OA/FA Dyn1 69/13.8kV 3-phase Power Transformer, 13.8kV 2500A, 25kA Metal Clad Switchgear, Control & Protective Requirements, Alarm & Annunciator, Metering System, Communication System, SCADA system
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Reinforcement of Dammam Power Plant 230/69 kV Substation
Modification of Existing Substations Consist of 57 Bay 4X255 MVA Transformer -155/205/255MVA 230/69/13.8kV Power Transformer,, 69kV 3-pole 3150/1250A 40kA Draw Out Type Live Circuit Breakers, Grounding and Switches, Insulators, Busbar & Fittings, 13.8kV Metal Clad Load Break Disconnect Switches, Outdoor Type
Client
Saudi Electricity Company Eastern Operating Area (SEC-EOA)
Reinforcement of Substation 8061 & 8072 Consist of 36 GIS Bay 6x60MVA Transformer,13.8kV Switchgear
Installation of 132kV 2000A GIS, 60MVA 132/13.8kV Power Transformer, Relays & Control Panels, 13.8kV Switchgear, SCADA Equipment, Fire Protection, DC System, Civil Works
Client
Saudi Electricity Company Central Operating Area (SEC-COA)
SAFWA 69/13.8kV Substation #2 and 69kV Double Circuit Overhead Transmission Line From QATIF BSP to SAFWA S/S
Installation of additional lighting protection for seven S/Ss in JIC
Installation of 69kV/31.5kA SF6 GIS, 30/40MVA, 69/13.8kV Power Transformer, 13.8kV,2500A.25kA Metal Clad Switchgear, Control and Protective Requirements, Remote Ends Protection Modification, Communication System, SCADA System
Client