Construction of AL-KHARJ Center-2 132/13.8kV Substation No.8713 in AL-KHARJ

  • Client : Saudi Electricity Company Central Operating Region
  • Contract type : EPC Contractor-Contract No.44000004011
  • Area : Central Area
  • Project Status : Project OnGoing
  • Nature of Work : Construction of AL-KHARJ Center-2 132/13.8kV Substation No.8713 in AL-KHARJ 132kV SF6 Gas Insulated Switchgear (GIS) with eleven (11) Nos. 132kV GIS CBs and Associated equipment, three (3) Nos. 132/13.8kV 67MVA Power Transformer, 13.8kV Switchgear with Forty Four (44) Nos.13.8kV Switchgear CBs panels, three (3) Nos. 13.8kV, 7MVAR Capacitor bank & associated equipment, auxiliary Equipment, cables and civil works. The project also includes, Extension of 132KV GIS one bay at remote end Substation with the necessary modifications/additions to the protection, control, communication, SCADA and associated equipment