EPC of Raising Overhead Power Lines & KFIP Power Substation Improvements

  • Client : Royal Commission
  • Contract type : EPC Contractor-Contract No.RC-071-C16R
  • Area : Eastern Area
  • Project Status : Project OnGoing
  • Nature of Work : PACKAGE A KFIP Power Substation Improvement The scope of works covers addition of one (1) 50/66, 7MVA Power Transformer, seven (7) 115kV GIS arrange in a double bus configuration and fourteen (14) numbers 34.5kV Switchgears including other associated protection, communication and SCADA. 11 KM 115kV Underground Cable (1Cx400mm2) from KFIP Substation to Jubail Southeast Substation in Jubail 1 PACKAGE B EPC of Raising Overhead Power Lines Modifications/Relocation/Rerouting of existing 230kV and 380kV Overhead Transmission Lines in Jubail 2 Replacement of single insulator string assembly with new double insulator string assembly on existing towers. Miscellaneous tower works for existing Overhead Transmission Lines